The West Virginia Department of Environmental Protection lifted their order halting Rover Pipeline construction on two segments where it found permit violations damaging streams in the northern part of the state, according to Kallanish Energy.

After inspectors found erosion-control failures that left sediment deposits in creeks and streams, the DEP ordered Rover Pipeline LLC to stop construction.

Last week the DEP found that permit violations were corrected. The reopened segments include a 36-mile stretch that extends from the Ohio border through Tyler and Wetzel counties to a compressor station at Sherwood in Doddridge County and a second that runs for six miles through Doddridge County.

Learn more: Kallanish Energy > West Virginia OKs construction on parts of Rover line

Subscribe to our mailing list

Get exclusive headlines from ShaleGasReporter.com emailed once a week (every Wednesday morning).

It's Free!

Leave a Comment

About Shale Gas Reporter

Farm and Dairy, a weekly newspaper located in Salem, Ohio, has been reporting on topics that interest farmers and landowners since 1914. Through the Shale Gas Reporter, we are dedicated to giving our readers unbiased and reliable information on shale gas development.

© Copyright 2024 - Farm and Dairy