Wednesday, May 12, 2021
Equitrans Midstream Corp. recently announced the Mountain Valley Pipeline’s projected in-service date has been pushed back again, according to the Charleston Gazette-Mail.
The company announced it was moving its targeted in-service date from the end of 2021 to the summer of 2022. It predicts the delay will add at least $200 million to the now $6.2 billion project.
The delay was caused by the project’s need to obtain water crossing permits.
The Mountain Valley Pipeline’s original completion date was anticipated for the end of 2018 at a cost of $3.5 billion.
Learn more: Charleston Gazette-Mail > Mountain Valley Pipeline delayed again as project cost keeps rising
Farm and Dairy, a weekly newspaper located in Salem, Ohio, has been reporting on topics that interest farmers and landowners since 1914. Through the Shale Gas Reporter, we are dedicated to giving our readers unbiased and reliable information on shale gas development.
© Copyright 2024 - Farm and Dairy